Apple revives controversial Athenry, Ireland datacenter plan
After protests previously caused it to abandon creating a datacenter in Athenry, Ireland, Apple has revived its plans and now intends to complete it by 2026.

Proposed Apple datacenter
Plans for a $1 billion Apple datacenter in Ireland's Atherny, County Galway, are back following previous protests and legal challenges. Apple had put the land up for sale, but has now filed for an extension on its original planning permission.
According to Data Center Dynamics, Apple's permission to build the datacenter expires in September 2021. The company is asking for an extension to November 2026 and says that it is actively planning to build by that date.
"Due to delays associated with the judicial processes initiated after the relevant planning consent issued and, more recently, the complications over the last year... arising from the Covid-19 pandemic, the subject development has not been brought to fruition," says Apple's application.
"It is the intention that the project will be undertaken as soon as practicable once suitable developers are identified," continues Apple. "It is anticipated the development will be completed within the extension period sought."
Apple originally bought land in Athenry, Galway, in 2014, with the intention of opening the billion datacenter by 2017. However, delays followed because of protests -- and a shortage of judges to hear the legal cases.
Apple prevailed in the case, but after a series of appeals abandoned the project in 2018. Reportedly, Apple put the land up for sale, though no buyer was found.
The decision over whether to grant the extension will be announced in August. It is likely to face more criticism, however, with one local politician arguing that the land should be bought by the government.
Separately, Ireland's Finance Minister has recently argued for a compromise on global corporate taxation. This follows the country's long-running dispute with the EU over the amount of tax it has charged Apple.
Keep up with everything Apple in the weekly AppleInsider Podcast -- and get a fast news update from AppleInsider Daily. Just say, "Hey, Siri," to your HomePod mini and ask for these podcasts, and our latest HomeKit Insider episode too.If you want an ad-free main AppleInsider Podcast experience, you can support the AppleInsider podcast by subscribing for $5 per month through Apple's Podcasts app, or via Patreon if you prefer any other podcast player.

Proposed Apple datacenter
Plans for a $1 billion Apple datacenter in Ireland's Atherny, County Galway, are back following previous protests and legal challenges. Apple had put the land up for sale, but has now filed for an extension on its original planning permission.
According to Data Center Dynamics, Apple's permission to build the datacenter expires in September 2021. The company is asking for an extension to November 2026 and says that it is actively planning to build by that date.
"Due to delays associated with the judicial processes initiated after the relevant planning consent issued and, more recently, the complications over the last year... arising from the Covid-19 pandemic, the subject development has not been brought to fruition," says Apple's application.
"It is the intention that the project will be undertaken as soon as practicable once suitable developers are identified," continues Apple. "It is anticipated the development will be completed within the extension period sought."
Apple originally bought land in Athenry, Galway, in 2014, with the intention of opening the billion datacenter by 2017. However, delays followed because of protests -- and a shortage of judges to hear the legal cases.
Apple prevailed in the case, but after a series of appeals abandoned the project in 2018. Reportedly, Apple put the land up for sale, though no buyer was found.
The decision over whether to grant the extension will be announced in August. It is likely to face more criticism, however, with one local politician arguing that the land should be bought by the government.
Separately, Ireland's Finance Minister has recently argued for a compromise on global corporate taxation. This follows the country's long-running dispute with the EU over the amount of tax it has charged Apple.
Keep up with everything Apple in the weekly AppleInsider Podcast -- and get a fast news update from AppleInsider Daily. Just say, "Hey, Siri," to your HomePod mini and ask for these podcasts, and our latest HomeKit Insider episode too.If you want an ad-free main AppleInsider Podcast experience, you can support the AppleInsider podcast by subscribing for $5 per month through Apple's Podcasts app, or via Patreon if you prefer any other podcast player.
Comments
Sounds like Apple is willing to ride out the next 2-3 years of appeals before they start to build. Smart to lock in future datacenter capacity, even if it is years away from going online
The chants of the hypocrites.
2 & 3) the political future of the ROI is not 'uncertain' because of Brexit, unless you're referring to the increasing likelihood of a successful pro-reunification vote in the North. The UK is a declining second-rate power, whereas the EU (of which the ROI is and will remain part) is the 800-lb gorilla.
4) to date the big problem with international comms has been the long-term, pervasive UK hoovering up of all ROI telecom data. The EU will surely be getting around to stopping this as a priority.
Data Centers provide clean, high paying jobs. One of them financed half of my working career and (along with a bit of investing) financed my retirement from it.